Planned Work

Start Date:
End Date:

Starting the week of April 8, 2024, Hydro Ottawa will be undertaking a project involving the replacement of aging hydro poles and equipment. We estimate that this project will be completed by August 16, 2024. 

Overall, this work will include:

  • pole replacement;  
  • lane reductions, sidewalk and bicycle lane closures at the site; and
  • tree trimming where required.

Impacted streets: Donald Street, Fullerton Avenue, Brant Street, Telford Avenue, Dunbrack, Street, Alesther Street, St-Laurent Boulevard, Sirois Avenue and Straby Avenue

Project start date: April 8, 2024

Project end date: August 16, 2024

Contractor on site: Teraflex Limited

Our qualified staff and contractors will conduct this work safely and efficiently, ensuring minimal inconvenience.

 